Basic Earned Value Management Metrics for Design Consultancies | BST Global (2024)

EVM is built on three metrics: Planned value, earned value, and actual cost.

Think of these metrics in terms of your project budget and schedule. Planned value represents how you expect to earn your project budget over the duration of the project. Earned value represents what you actually earn as the project progresses. Actual cost represents what you spend to complete work throughout the project.

At first glance, these terms might seem pretty straightforward, but let’s translate them into even more meaningful terms for a professional services firm.

1. Planned Value = Planned Revenue

Planned value (PV) provides the baseline for tracking project performance in EVM, representing the value a project is expected to deliver over its duration. In the context of consulting projects, PV represents the revenue a project is expected to earn through completion, adding up to the overall project fee or budget. In other words, planned value is planned revenue.

Planned revenue may be expressed as an overall figure for an entire project, or it can be divided across a project’s work breakdown structure (WBS). Additionally, planned revenue can be spread across time periods (e.g., weeks or months), to represent the timing of when a project is expected to earn revenue based on anticipated completion of project deliverables.

Basic Earned Value Management Metrics for Design Consultancies | BST Global (1)

2. Earned Value = Earned Revenue

The second metric of EVM is earned value (EV). For design consultancies, this is more aptly termed earned revenue; it represents the revenue a project earns as work is performed and milestones are achieved.

There are multiple ways to earn revenue on a project. Revenue may be earned when the project team charges hours or expenses to the project. Hours charged on a timesheet may be converted into revenue via contracted labor multipliers or bill rate schedules. Expense charges — like travel, printing, or subcontractor expenses — may be converted into revenue via contracted expense multipliers or unit pricing rate schedules.

Revenue may also be earned as project managers assess percent complete across the project WBS. These assessments are often done monthly, and usually stem from progress to-date and how much work remains.

Regardless of how it’s calculated, earned revenue is often governed by planned revenue, which in turn is tied to contract terms. For instance, if the contract dictates a lump sum or fixed fee, earned revenue cannot exceed this amount. A similar limit applies for projects that have cost-plus contracts up to a predetermined maximum amount.

3. Actual Cost = Actual Effort

The final core EVM metric, actual cost (AC), is the market (or retail) value of cost a project incurs as work is performed. This metric provides consultancies with a way to compare how much effort has been expended on a project in relation to the planned revenue and earned revenue on the project. As such, in a professional services context, this metric is better termed actual effort.

In many ways, actual effort accrues on a project similar to the way earned revenue accrues. Actual effort is the result of labor or expense charges being posted to a project, with these charges being converted into actual effort via contracted labor and expense pricing terms.

However, there are two significant differences between actual effort and earned revenue. First, actual effort cannot be calculated or adjusted by percent complete assessments — actual effort is purely a function of the labor or expense charges posted to the project. Second, actual effort is not bound by planned revenue. As your team continues to work on a project, actual effort continues to accrue, even if earned revenue is capped by planned revenue limits.

Another way to understand actual effort comes from its relationship to direct cost. While direct cost represents the cost to a consultancy for services delivered, actual effort represents the market value of services delivered. And while some consultancies may incorporate direct cost into their project management methodology to measure project multipliers or other margin-based metrics, direct cost is not core to EVM.

Closing Thoughts

In order to leverage EVM effectively, a design consultancy must translate EVM’s three core metrics to fit the unique way professional services projects are contracted and delivered. With this understanding, a firm can take the next step of defining additional metrics and thresholds that leverage these core metrics, thus gaining greater insight into project status and enabling early warning indicators of project issues.

I’ll discuss this next step in the third post of this EVM series. In the meantime, please share your EVM questions and/or experiences in a comment below!

Author’s Note: This is the second article in a four-post series on the use of Earned Value Management in professional services organizations.

Basic Earned Value Management Metrics for Design Consultancies | BST Global (2024)

FAQs

What are the three basic metrics of earned value management? ›

EVM is built on three metrics: Planned value, earned value, and actual cost. Think of these metrics in terms of your project budget and schedule.

What are the three components of EVM? ›

Key Components of EVM
  • Planned Value (PV) Planned Value, often called the Budgeted Cost of Work Scheduled (BCWS), is a critical component of EVM. ...
  • Earned Value (EV) ...
  • Actual Cost (AC) ...
  • Cost Performance Index (CPI) ...
  • Schedule Performance Index (SPI) ...
  • Variance Analysis. ...
  • Performance Indices Thresholds.
Dec 13, 2023

How to calculate EVM in project management? ›

You can calculate the EV of a project by multiplying the percentage complete by the total project budget. For example, let's say you're 60% done, and your project budget is $100,000 — your earned value is then $60,000.

What is the 50 50 rule in project management? ›

With the 50/50 rule, managers assess 50% of a project's value at the start and 50% when it's complete. So, for example, if a project team is working on a fence that goes around an entire property, they can use their progress on the first portion of the fence to expect their total time and spend.

What are the three key dimensions used in earned value? ›

There are three key components to earned value: Planned Value, Earned Value and Actual Cost. – PV is the physical work scheduled or “what you plan to do”. – EV is the quantification of the “worth” of the work done to date or “what you physically accomplished”.

What are the three key process metrics? ›

There are three major categories of process metrics, which include: Static process metrics: Relate to the properties of a defined process. Dynamic process metrics: Relate to the performance of a process. Process evolution metrics: Relate to making changes within a process over time.

What is the basic EVM? ›

Earned value management (EVM) is a project management methodology that integrates schedule, costs, and scope to measure project performance. Based on planned and actual values, EVM predicts the future and enables project managers to adjust accordingly.

What are the principles of EVM? ›

EVM Principles. At its essence, Earned Value is a measure of project performance comparing work completed against work planned, as of a given date. It is used to (1) measure, (2) forecast, and (3) improve project performance for an organization.

What are the key components of earned value analysis? ›

Key Components in Earned Value Analysis

Planned Cost/Planned Value (PC or PV): This represents the estimated cost of the work scheduled to be completed by a certain date. It sets the baseline against which actual progress is measured. Earned Value (EV): This represents the value of work actually completed to date.

What are EVM formulas? ›

EV = Total Project Budget * Budget % Completed. Cost Variance. CV = EV – AC. Schedule Variance. SV = EV – PV.

How do you measure EVM? ›

EVM is computed by comparing the measured signal with an ideal reference signal to determine the error vector. The 89601A software displays the computed results as both a percentage, and logarithmic value (in dB). You can also display the normalized EVM value that is called out in the 802.11B specification.

How are EVM metrics used in agile? ›

Agile Projects and EVM

The key benefit of using EVM/EVA for these projects was that the mathematical combination of cost/spend and technical progress measurement metrics gave project managers, and thus stakeholders, a set of standard, forward-looking metrics on which to make timely decisions.

What is the golden rule of project management? ›

#1: Define your objectives

Once you have a good understanding of the overall goal, you can start to break it down into more specific objectives. Some things to keep in mind when defining your objectives: Make sure they are SMART: Specific, Measurable, Achievable, Relevant, and Time-bound.

What is the 80 hour rule in project management? ›

8-80 rule states that work packages must be between eight hours and eighty hours chunks of work. If the projects are big, then work packages can be around 80 hour chunks of work. For small projects the work packages can be around 8 hours, or it could be anything between 8 hours and 80 hours.

What is the 80 20 rule in project? ›

Otherwise known as the 80/20 rule, the Pareto rule is a tool that can be used to improve project management efficiency. The rule states that 80% of the results of a project come from 20% of the work. Therefore, by focusing on the 20% of work that is most important, we can improve the efficiency of a project.

What are the basic elements of earned value management? ›

EVM consists of the following three basic elements: Planned Value. Actual Cost. Earned Value.

What are the three classifications or earned value techniques? ›

EVM Budget summary matrix

This determination begins with classifying work tasks as one of three types: discrete, apportioned effort, or level of effort (LOE).

What are the three Earned Value Analysis Formulae? ›

Earned Value Calculations
• Cost Variance: CV = EV – AC• Cost Performance Index: CPI = EV/AC
• Schedule Variance: SV = EV – PV• Schedule Performance Index: SPI = EV/PV

What are the three variances of earned value? ›

Part A) Three variances are 1) Schedule variance (SV) = Earned value - planned value 2) Time variance = Scheduled time - variance time 3) Cost variance= Earned value - total cost Significance:- A positive schedule variance means the project is ah…

Top Articles
Visa Platinum Debit Card - Apply for Platinum Debit Card Online
Five New Ways to Handle, “I’m too busy” | Mr. Inside Sales
How To Start a Consignment Shop in 12 Steps (2024) - Shopify
It’s Time to Answer Your Questions About Super Bowl LVII (Published 2023)
Shoe Game Lit Svg
Star Sessions Imx
Satyaprem Ki Katha review: Kartik Aaryan, Kiara Advani shine in this pure love story on a sensitive subject
Pga Scores Cbs
Missing 2023 Showtimes Near Cinemark West Springfield 15 And Xd
FFXIV Immortal Flames Hunting Log Guide
San Diego Terminal 2 Parking Promo Code
Fototour verlassener Fliegerhorst Schönwald [Lost Place Brandenburg]
Costco in Hawthorne (14501 Hindry Ave)
Chase Claypool Pfr
Music Archives | Hotel Grand Bach - Hotel GrandBach
Does Pappadeaux Pay Weekly
Obituary | Shawn Alexander | Russell Funeral Home, Inc.
Watch TV shows online - JustWatch
Bahsid Mclean Uncensored Photo
Houses and Apartments For Rent in Maastricht
Pekin Soccer Tournament
Testberichte zu E-Bikes & Fahrrädern von PROPHETE.
Putin advierte que si se permite a Ucrania usar misiles de largo alcance, los países de la OTAN estarán en guerra con Rusia - BBC News Mundo
Ceramic tiles vs vitrified tiles: Which one should you choose? - Building And Interiors
Bellin Patient Portal
Airtable Concatenate
Milwaukee Nickname Crossword Clue
Coindraw App
Narragansett Bay Cruising - A Complete Guide: Explore Newport, Providence & More
Tinyzonehd
1636 Pokemon Fire Red U Squirrels Download
2021 Tesla Model 3 Standard Range Pl electric for sale - Portland, OR - craigslist
Lesson 1.1 Practice B Geometry Answers
Manuel Pihakis Obituary
Luciipurrrr_
Serenity Of Lathrop - Manteca Photos
Http://N14.Ultipro.com
Craigs List Stockton
Grapes And Hops Festival Jamestown Ny
Robeson County Mugshots 2022
Smith And Wesson Nra Instructor Discount
The Minneapolis Journal from Minneapolis, Minnesota
Cheetah Pitbull For Sale
Cygenoth
craigslist: modesto jobs, apartments, for sale, services, community, and events
Kenner And Stevens Funeral Home
Joblink Maine
Sherwin Source Intranet
Sapphire Pine Grove
All Buttons In Blox Fruits
Rovert Wrestling
M Life Insider
Latest Posts
Article information

Author: Terence Hammes MD

Last Updated:

Views: 6214

Rating: 4.9 / 5 (49 voted)

Reviews: 88% of readers found this page helpful

Author information

Name: Terence Hammes MD

Birthday: 1992-04-11

Address: Suite 408 9446 Mercy Mews, West Roxie, CT 04904

Phone: +50312511349175

Job: Product Consulting Liaison

Hobby: Jogging, Motor sports, Nordic skating, Jigsaw puzzles, Bird watching, Nordic skating, Sculpting

Introduction: My name is Terence Hammes MD, I am a inexpensive, energetic, jolly, faithful, cheerful, proud, rich person who loves writing and wants to share my knowledge and understanding with you.