Determine Cost Status (2024)

Once the schedule status is determined it’s time to figure out where the project stands in terms of budget. We seek to determine if the project is over or under budget, and how far.

To do this we will calculate two more variables from the initial three we gathered from the project data. They are very similar to the schedule-related variables but require their own interpretation and understanding.

  1. Cost Variance (CV)
  2. Cost Performance Index (CPI)

Cost Variance (CV)

The Cost Variance, usually abbreviated CV, answers the following question:

  • How far over or under budget is the project?

It represents, simply, the amount that the task is over or underits budget, interpolated to the current date. It must be calculated for each task and summed to produce the overall project’s cost variance. The formula is:

CV = EV – AC

  • If CV is negative, the task is over budget.
  • If CV is zero, the task is on budget.
  • If CV is positive, the task is under budget.

For example,

  • CV = -$1,000 means the project is over budget.
  • CV = $0 means the project is right on budget.
  • CV = $1,000 means the project is under budget.

For the CV, like the SV,positive is good.

The CV can be compared to the task’s budget, for example if the above cost variance of $1,000 applied to a task with a budget of $2,000 it has incurred an overrun equal to 50% of the task, a seemingly existentialproblem, whereas if the task budget was $100,000 the overrun is small and could probably be mitigated somewhere else.

In our running example task, in which we have already calculated the schedule status on theprevious tutorial page, we will add a column to the table for CV.

CV = EV – AC
CV = $2,000 – $4,500 = -$2,500.

IDNameStartEndBACPVEVACSVSPICV
100Set up DatabaseMar. 1Mar.10$10,000$3,000$2,000$4,500-$1,0000.67-$2,500

The taskis $2,500 over budget on a task value of $10,000. If everything goes according to plan from here on, the task will finish at $12,500. There is clearly a budget problem as well as a schedule one.

Cost Performance Index (CPI)

The Cost Performance Index (CPI),like the Cost Variance, is a measure of the cost performance of the project, but it is a relative instead of an absolute measure. It answers the question:

  • How efficiently are we using our resources?

The formula is:

CPI = EV / AC

  • If CPI is less than 1, the task isover budget.
  • If CPI is zero, the task is on budget.
  • If CPI is greater than 1, the task isunder budget.

For example,

  • CPI = 0 means the project work has not started.
  • CPI = 0.5 means the project has spent twice amount that it should have at this point.
  • CPI = 1.0 means the project is on schedule.
  • CPI = 2.0 means the project has spenthalf the amount that it should have at this point.

For theCPI, like the SPI, greater than 1.0 is good.

We will add a column to the table for CPI.

CPI = EV / AC
CPI = $2,000 / $4,500 = 0.44.

IDNameStartEndBACPVEVACSVSPICVCPI
100Set up DatabaseMar. 1Mar.10$10,000$3,000$2,000$4,500-$1,0000.67-$2,5000.44

The taskhas spent morethan twice what it should have at this point.

In short, this task has a minor schedule problem and a major cost problem. A quick glance at the table, where CPI = 0.44 indicates that this task is in danger of extending the project’s completion date or driving the project over budget. Neither of thosehave occurred yet, but 3 days into our 10 day task the project manager can clearly see that action needs to be taken.

Interpretation

Just like with the schedule variance, it is a well understood concept that a project that goes over budget early on will finish over budget. Thus, it is extremely important to watch the CV and CPI early and often, being sure to address the small variances, thus fostering a culture of performance for the project from the beginning.

Graphing the trend of the CV and CPI through multiple status points can identify trends that can be enlightening. Often unexpected one time expenses can be mitigated if the project is consistently under budget elsewhere. But consistent over spending leaves no room for unexpected events.

In fact, almost everything unexpected that happens on projects requires more money. It would be nice if you arrived at work one morning to realize you’re going to save some money on your project without any sacrifice, but this is very rare. It is important to make sure thatthe CPI is monitored and acted upon to ensure the maximumefficiency, and thus ability to absorb small one time items.

The CV and CPI give you an at-a-glance snapshot of the project’s budget status at any given time. They are very similar to the SV and SPI which give you the same snapshot as it relates to schedule. On the next page we will calculate four variables that represent the forecast of the current status to the end of the project, an extrapolation if you will.

Navigation

  • Previous Page: Determine Schedule Status
  • Next Page: Earned Value Forecasting
  • Home: Earned Value Tutorial
Determine Cost Status (2024)

FAQs

What is an example of a cost analysis? ›

Here's an example of cost analysis for a project:A clothing company wants to determine if they might launch a new clothing line by next spring. They decide that a cost analysis would offer them insight into how much they would earn from the project to compare profit and costs.

How to write a cost analysis report? ›

Use these steps to help you complete a project cost analysis:
  1. Determine a set price. ...
  2. List all associated costs. ...
  3. Convert cost to monetary value. ...
  4. List estimated benefits. ...
  5. Convert benefits to monetary value. ...
  6. Add costs together. ...
  7. Perform subtraction. ...
  8. Compare to your decided price.
Mar 10, 2023

What is the formula for cost estimation? ›

The goal of each cost estimation method is to estimate fixed and variable costs and to describe this estimate in the form of Y = f + vX. That is, Total mixed cost = Total fixed cost + (Unit variable cost × Number of units).

How to do a cost estimate? ›

How does cost estimating work? 6 steps to learn
  1. Agree on estimating basis. ...
  2. Collect scope documentation. ...
  3. Estimate direct cost. ...
  4. Estimate other costs and apply factors, indexation and escalation. ...
  5. Peer review. ...
  6. Finalize basis of estimate report and send estimate for approval.
Aug 4, 2023

What is cost determination? ›

Cost determination is the process of identifying and measuring the costs incurred by a business or an organization in producing or delivering its goods or services. Cost determination is essential for various purposes, such as pricing, budgeting, profitability analysis, decision making, and performance evaluation.

What is the formula for cost analysis? ›

The cost-benefit analysis involves comparing the monetary benefits of a project to the costs. The formula to calculate the cost-benefit analysis ratio divides the projected present value (PV) of benefit by the present value (PV) of cost attributable to a project.

What is a short note on cost analysis? ›

Cost analysis is a financial management process that involves the identification, classification, and evaluation of all expenses incurred by an organization, project, or product. It aims to determine the total cost of production, operation, or a specific activity.

What is an example of a cost effective analysis? ›

A cost-effectiveness ratio is the net cost divided by changes in health outcomes. Examples include cost per case of disease prevented or cost per death averted. However, if the net costs are negative (which means a more effective intervention is less costly), the results are reported as net cost savings.

How do you perform a should cost analysis? ›

Steps in a should-cost analysis
  1. Carry out an input study. An input study seeks to understand what parts are required to produce the final product. ...
  2. Understand what processes are involved. ...
  3. Perform cost modeling. ...
  4. Create a report.

What is cost estimation in simple words? ›

Cost estimation in project management is the process of forecasting the financial and other resources needed to complete a project within a defined scope. Cost estimation accounts for each element required for the project — from materials to labor — and calculates a total amount that determines a project's budget.

How do you estimate total cost? ›

The formula to calculate total cost is the following: TC (total cost) = TFC (total fixed cost) + TVC (total variable cost).

How is cost calculated? ›

The Total Cost Formula, represented as (Fixed Cost + Variable Cost) / Number of Units Produced, provides insights into the cost structure of a business, helping determine profitability.

How do you write a simple estimate? ›

You can create estimates easily by breaking the process down into 5 steps:
  1. Review the scope of the project and talk to your client about expectations.
  2. Draft an approximate timeline.
  3. Price out any subcontractors if you need additional labor.
  4. Calculate your materials costs and business expenses.

What is the easiest way to estimate? ›

Rounding is the most common way to start estimating. Rounding means to estimate a number to its closest desired digit. Often numbers are rounded to whole numbers to avoid working with decimals or fractions. For example: is rounded down to to make it easier to work with.

How do you estimate correctly? ›

4 Steps to precise task duration estimates
  1. Step #1: Look at the task from a bird's eye view. ...
  2. Step #2: Break down your task into chunks. ...
  3. Step #3: Roughly calculate the time for each step. ...
  4. Step #4: Add more time, just in case. ...
  5. Conclusion: Keep the data up your sleeve.
Sep 8, 2023

What do you mean by cost analysis? ›

1. : the act of breaking down a cost summary into its constituents and studying and reporting on each factor. 2. : the comparison of costs (as of standard with actual or for a given period with another) for the purpose of disclosing and reporting on conditions subject to improvement.

What is an example of a relevant cost analysis? ›

Increases or decreases in cash flows caused by a project are relevant. So, if an old product is discontinued three years early to make room for a new product, the revenue and cost decreases relating to the old product are relevant, as are the revenue and cost increases on the new.

What is an example of a product cost analysis? ›

Examples of product costing include determining the total expenses to produce a smartphone (materials, assembly labor, factory overhead) or calculating the cost of producing a handmade artisanal chair (wood, varnish, craftsman's labor).

Top Articles
Celebrities Who Own Ethereum in 2024 • Benzinga
Convert 1000 HASH to USD - HASH to US Dollar Converter | CoinCodex
Nullreferenceexception 7 Days To Die
Cranes For Sale in United States| IronPlanet
Rubratings Tampa
Online Reading Resources for Students & Teachers | Raz-Kids
Gw2 Legendary Amulet
Jesse Mckinzie Auctioneer
Locate Td Bank Near Me
Restaurants Near Paramount Theater Cedar Rapids
7 Fly Traps For Effective Pest Control
History of Osceola County
Overton Funeral Home Waterloo Iowa
Mflwer
Richland Ecampus
Accuweather Mold Count
Everything you need to know about Costco Travel (and why I love it) - The Points Guy
Publix Super Market At Rainbow Square Shopping Center Dunnellon Photos
Crawlers List Chicago
Pearson Correlation Coefficient
[PDF] NAVY RESERVE PERSONNEL MANUAL - Free Download PDF
Foolproof Module 6 Test Answers
Die 8 Rollen einer Führungskraft
4 Methods to Fix “Vortex Mods Cannot Be Deployed” Issue - MiniTool Partition Wizard
Enduring Word John 15
Stickley Furniture
Core Relief Texas
Rek Funerals
Revelry Room Seattle
Chadrad Swap Shop
The 50 Best Albums of 2023
Space Marine 2 Error Code 4: Connection Lost [Solved]
The Complete Guide To The Infamous "imskirby Incident"
Raisya Crow on LinkedIn: Breckie Hill Shower Video viral Cucumber Leaks VIDEO Click to watch full…
Aliciabibs
Rage Of Harrogath Bugged
Walgreens Agrees to Pay $106.8M to Resolve Allegations It Billed the Government for Prescriptions Never Dispensed
877-292-0545
Academy Sports New Bern Nc Coupons
What Is A K 56 Pink Pill?
Pokemon Reborn Gyms
The power of the NFL, its data, and the shift to CTV
What to Do at The 2024 Charlotte International Arts Festival | Queen City Nerve
Costner-Maloy Funeral Home Obituaries
De boeken van Val McDermid op volgorde
Strange World Showtimes Near Atlas Cinemas Great Lakes Stadium 16
Estes4Me Payroll
Anthony Weary Obituary Erie Pa
Comenity/Banter
Varsity Competition Results 2022
Latest Posts
Article information

Author: Jeremiah Abshire

Last Updated:

Views: 5802

Rating: 4.3 / 5 (54 voted)

Reviews: 93% of readers found this page helpful

Author information

Name: Jeremiah Abshire

Birthday: 1993-09-14

Address: Apt. 425 92748 Jannie Centers, Port Nikitaville, VT 82110

Phone: +8096210939894

Job: Lead Healthcare Manager

Hobby: Watching movies, Watching movies, Knapping, LARPing, Coffee roasting, Lacemaking, Gaming

Introduction: My name is Jeremiah Abshire, I am a outstanding, kind, clever, hilarious, curious, hilarious, outstanding person who loves writing and wants to share my knowledge and understanding with you.