Earned Value Management Example & Tutorial - projectcubicle (2024)

One week ago, we received an email from one of our readers asking where to find earned value management exercises and answers. In this earned value management tutorial, we will analyze an Earned Value Management Example. Basically, earned value analysis is an efficient technique to realize and manage the project’s performance.

Table of Contents

Organizations across all the industries use Earned Earned Value analysis techniques to understand the health of their projects. Customers and/or the stakeholders usually ask Project managers the following famous questions:

How is the project going? or How is the performance of the project?

One traditional technique often used by project managers is to compare the planned and the actual cost curves to answer.

If the actual cost is less than the planned cost, can we say that the project’s cost performance is well ? or are we ahead of schedule?

The planned and the actual curve comparison is not enough to understand how the project is going. Let’s go deeper into the topic and analyze “Earned Value Management” and formulas first, then, make the Earned Value calculations by using an example.

The Concept of Earned Value Management (EVM)

Common project management methods use the actual vs. planned model to monitor how the project is successful from a budgeting viewpoint. But these kinds of traditional methods do not keep in mind the value of the work performed in a given period. Earned Value Management (EVM) is a project management technique for measuring project performance and progress.

While using the actual vs. planned model, only the under or overspending can be reported. It does not show your progress performance. For instance, while being ahead of the plan and making enormous progress, overspending could be seen and as a result, the project will finish earlier.


However, if there is no method for understanding the value of work performed, you have no chance to report what the main reasons for the overspend are. Project percent complete values can be monitored from the work schedule but it is not easy to link this percent complete value with actual cost and budget.
For better understanding, let’s analyze a sample project in terms of actual vs. planned and use earned value to understand what are the benefits of this method.

Basic Elements of EVM

Earned Valueanalysis uses three key metrics which are the planned value, actual cost, and the EV as illustrated in the figure below.

Earned Value Management Example & Tutorial - projectcubicle (1)

PLANNED VALUE ACTUAL COST EV

Planned Value (PV), is the budgeted cost for the work scheduled or budgeted cost of work scheduled (BCWS).

Actual Costs (AC), the actual cost for the work accomplished, or actual cost of work performed (ACWP).

Earned Value (EV)is the percent of the total budget actually completed at a point in a given time. It is also known as the budgeted cost of work performed(BCWP)

For example, if the total scope of work is to install 1000 transmission towers, and 600 of them are installed, the progress of the work is 60% complete. If the total budgeted cost of this work is $3 M, the EV is $3 M x 0,6 = $ 1,8 M.

Earned Value Calculations

EV Calculation formulas are;

Cost Variance:CV = EV – AC

Cost Performance Index:CPI = EV/AC

Schedule Variance:SV = EV – PV

Schedule Performance Index:SPI = EV/PV

IfCost Performance Index (CPI) is less than oneand a negative CV means that the project cost performance is below the plan.

If the Schedule Performance Index (SPI) isgreater than one and a positive SV means that you completed more work than planned. But don’t forget thatSPI > 1 does not always mean that you are ahead of schedule. You should check the critical path and determine if you are behind or ahead of schedule.

Earned Value Management Example

Earned Value Management Example & Tutorial - projectcubicle (2)

Let’s assume a 12-month railway project that is planned to spend $3M per month for a total budget at completion (BAC) of $36M. The project is 2 months along and according to the planned vs. actual cost figures is underspent by 50%.
We could assume therefore that the project is going well because it’s costing less than planned.

But after 2 months of work, 10 % of work has been completed so “EV” is 10% of the total $36M budget, which is $3.6M.

Budget at Completion (BAC) : $36M
Planned Value (PV) for 2 Months: $6M
EV: $3.6M
Actual Cost (AC): $3M

Schedule Variance (SV) : (Earned Value – Planned Value) = $3.6 – $6 = – $2.4 Behind the schedule
Cost Variance (CV): (Earned Value – Actual Cost) = $ 600K Under Budget
Cost Performance Index (CPI): (Earned Value / Actual Cost) = 1.2
Schedule Performance Index (SPI): (Earned value / Planned value) = 0.6
Estimate at Completion (EAC) : (Budget at Completion / Cost Performance Index) =$30M


Estimate to Completion (ETC): (Budget at Completion – Earned Value)/ Cost Performance Index = $27 M

Time to Complete: (Budget at Completion – EV)/ Schedule Performance Index =54 Months

By taking into consideration this performance, this railway project will be completed in 54 months with a $36 M budget.

Summary

Earned value is a powerful technique that provides project information with the help of project schedule, planned value, actual value, and earned value calculations. It is widely used by stakeholders to understand the real performance of the project. Earned Value Management provides an early warning system for the project teams regarding the issues affecting the budget and schedule. This helps the project teams to employ methods to put the project back on track.

In this Earned Value Management tutorial we analyzed an Earned Value Management Example which emphasizes the benefits of this system in project management. At the beginning and the end of a project, because of the lack of coordination between crews and equipment, low performance will occur. It is better to be aware of delays in the early stages by using project management tools to ensure project success.

External References

pmi.org

See Also

Project Status Report Template

Earned Value Management Example & Tutorial - projectcubicle (3)

Fernando Aldena

I am a Civil Engineer in HES Consultancy Limited, experience as Director and Resident of Works and Technical, Financial and Administrative Project Audit. I have skills in the area of Procurement, Tenders and Contracting. I am PMP and PRINCE2 Certified. Monitoring and Control with the Earned Value Method.

Tags: earned value analysis example problem earned value example problems earned value management example earned value management examples for project management earned value management exercises and answers earned value management tutorial

Earned Value Management Example & Tutorial - projectcubicle (2024)

FAQs

What is an example of earned value management in project management? ›

You can calculate the EV of a project by multiplying the percentage complete by the total project budget. For example, let's say you're 60% done, and your project budget is $100,000 — your earned value is then $60,000.

How to calculate earned value example? ›

Eearned Value = Percent complete (actual) x Task Budget.

For example, if the actual percent complete is 50% and the task budget is $10,000 then the earned value of the project is $5,000, 50% of the budget provided for this project.

What is the formula for EVM in project management? ›

It is typically based on the progress of completing the project's tasks or deliverables. EV = BAC * Actual % Complete, where BAC is the Budget at Completion, and Actual % Complete is the percentage of actual work completed up to the current reporting period.

What is earned value for dummies? ›

The definition of earned value management for dummies

Time - Comparing the amount of work which has been done compared to what was scheduled (are we going to deliver in time?) Cost - Comparing the amount we have spent to the original project budget (have we spent more or less than we had planned)

How do project managers use earned value management? ›

Earned Value Analysis (EVA) is a method that allows the project manager to measure the amount of work actually performed on a project beyond the basic review of cost and schedule reports. EVA provides a method that permits the project to be measured by progress achieved.

What is the 50 50 rule in PMP? ›

With the 50/50 rule, managers assess 50% of a project's value at the start and 50% when it's complete. So, for example, if a project team is working on a fence that goes around an entire property, they can use their progress on the first portion of the fence to expect their total time and spend.

What are the three key EVM metrics? ›

EVM is built on three metrics: Planned value, earned value, and actual cost. Think of these metrics in terms of your project budget and schedule. Planned value represents how you expect to earn your project budget over the duration of the project.

What is the earned value method of a project? ›

Earned Value is a well-known project management tool that uses information on cost, schedule and work performance to establish the current status of the project. By means of a few simple rates, it allows the manager to extrapolate current trends to predict their likely final effect.

What are the three earned value methods? ›

EVM Budget summary matrix

This determination begins with classifying work tasks as one of three types: discrete, apportioned effort, or level of effort (LOE).

How to calculate complete in EVM? ›

Duration % Complete – calculated as the delta between the Original (or Planned) Duration and the Remaining Duration divided by the Planned Duration.

How EVM can be used to measure project performance? ›

Using EVM to evaluate performance is all about comparing where you are to where you planned to be. Look at metrics like Cost Performance Index (CPI) and Schedule Performance Index (SPI). If CPI is greater than 1, you're under budget. If SPI is greater than 1, you're ahead of schedule.

What is the formula for earned value in Excel? ›

Walk-Through: How To Calculate Earned Value

As I mentioned above, earned value is EV = (PV)(% complete), but how do you know the % complete?

What is an earned value chart? ›

What is an Earned Value chart? An earned value chart is a way of displaying earned value management metrics over time. Typically, the chart has lines that represent budget (planned project cost), actual cost and earned value, which is a measure of how much progress has been made.

How to make an earned value chart in Excel? ›

Choose View > Table, then choose More Tables. In the list, select Earned Value, Earned Value Cost Indicators, or Earned Value Schedule Indicators. If you're not sure which table, just pick Earned Value. Choose Apply.

What are earned value metrics? ›

The earned value metric is actually the planned value of the work that has been accomplished, but it is often referred to as the budgeted cost for work performed (BCWP). The baseline plan that performance is measured against is an aggregation of the timephased value of the work planned to be performed.

What is an example of value management? ›

Earned value management example – 1. Let's imagine we are building a wind power plant. The project is set to be completed in 10 months with an estimated cost of $500,000. The project has been running for 5 months now, the team has spent $220,000 and completed an amount of work worth $255,000.

What is PV in project management? ›

Planned Value (PV) is a project management term used to describe the budgeted cost of work scheduled for a specific period of time. It is also known as Budgeted Cost of Work Scheduled (BCWS).

Top Articles
Netflix or Disney Plus: Decide Which Streaming Service Fits You Best
Accessing VMs with RDP | Skytap help and documentation
Www.1Tamilmv.cafe
Cooking Chutney | Ask Nigella.com
4-Hour Private ATV Riding Experience in Adirondacks 2024 on Cool Destinations
Plaza Nails Clifton
COLA Takes Effect With Sept. 30 Benefit Payment
Amtrust Bank Cd Rates
Think Of As Similar Crossword
More Apt To Complain Crossword
Category: Star Wars: Galaxy of Heroes | EA Forums
What's New on Hulu in October 2023
Zachary Zulock Linkedin
Walmart Windshield Wiper Blades
Viha Email Login
Available Training - Acadis® Portal
Me Cojo A Mama Borracha
Virginia New Year's Millionaire Raffle 2022
Hermitcraft Texture Pack
Wgu Academy Phone Number
Kirksey's Mortuary - Birmingham - Alabama - Funeral Homes | Tribute Archive
Is Windbound Multiplayer
Thick Ebony Trans
Craigs List Jonesboro Ar
Kirsten Hatfield Crime Junkie
Speedstepper
Receptionist Position Near Me
Winterset Rants And Raves
Korg Forums :: View topic
Why comparing against exchange rates from Google is wrong
Leland Nc Craigslist
Sinfuldeeds Vietnamese Rmt
Dying Light Nexus
Cheetah Pitbull For Sale
World Social Protection Report 2024-26: Universal social protection for climate action and a just transition
Henry Ford’s Greatest Achievements and Inventions - World History Edu
Tedit Calamity
Dinar Detectives Cracking the Code of the Iraqi Dinar Market
Joey Gentile Lpsg
Pink Runtz Strain, The Ultimate Guide
Academic Calendar / Academics / Home
Streameast Io Soccer
Xre 00251
Vci Classified Paducah
Kaamel Hasaun Wikipedia
UNC Charlotte Admission Requirements
Barback Salary in 2024: Comprehensive Guide | OysterLink
116 Cubic Inches To Cc
28 Mm Zwart Spaanplaat Gemelamineerd (U999 ST9 Matte | RAL9005) Op Maat | Zagen Op Mm + ABS Kantenband
North Park Produce Poway Weekly Ad
Coors Field Seats In The Shade
Latest Posts
Article information

Author: Neely Ledner

Last Updated:

Views: 6152

Rating: 4.1 / 5 (62 voted)

Reviews: 93% of readers found this page helpful

Author information

Name: Neely Ledner

Birthday: 1998-06-09

Address: 443 Barrows Terrace, New Jodyberg, CO 57462-5329

Phone: +2433516856029

Job: Central Legal Facilitator

Hobby: Backpacking, Jogging, Magic, Driving, Macrame, Embroidery, Foraging

Introduction: My name is Neely Ledner, I am a bright, determined, beautiful, adventurous, adventurous, spotless, calm person who loves writing and wants to share my knowledge and understanding with you.