Filters in Project Plan 365 (2024)

What are the Overview filters?

The Overview filters are: All Tasks, All Resources, Created after…, Critical, Current Sprint, Date Range…, Group, Manually Scheduled Tasks, Milestones, Resource Group…, Resource Range, Summary Tasks, Task Board Tasks, Task Range…, Tasks with a Task Calendar Assigned, Tasks with Deadlines,Tasks with Duration <8, Tasks with Estimated Durations, Tasks with Fixed Dates, Tasks without Dates, Top Level Tasks.

What does the "Filter" functionality do?

The "Filter" functionality allows the user to view a particular type of information in the project by displaying only the information the user is interested in and hiding the rest.

How to apply a custom field filter?

We are sorry, but at this point you cannot add a custom field filter. You can apply an autofilter.

How do I apply the auto-scheduled tasks filter?

We are sorry, but at this point, this filter is not available in the application.

What filters can I apply in Resource views?

In Resource views you can apply the following filters: All Resources, Group, Overallocated Resources, Resource Cost, Resource Material, Resource Range, Resource Work, Unstarted Assignments, Work Complete, Work Incomplete.

How do I remove a filter?

In order to remove a filter, apply the "All Tasks" filter. The "All Tasks" filter is the default filter and allows seeing all tasks, regardless of their particularities.

How can I apply a filter in the Project Plan 365 app?

In order to apply a filter, go to menu Project - Filter and select the desired Filter.

Filters in Project Plan 365 (1)

What does the "All Tasks" filter do?

The "All Tasks" filter allows seeing all tasks, regardless of their particularities.

How do I apply the "All Tasks" filter?

In order to apply the "All Tasks" filter, go to menu Project - Filter and select All Tasks or select More Filters and select All Tasks and click on Apply button.

What does the "All Resources" filter do?

The "All Resources" filter allows seeing all resources, regardless of their particularities.

How do I apply the "All Resources" filter?

In order to apply the "All Resources" filter, go to menu Project - Filter and select All Resources or select More Filters and select All Resources and click on Apply button.

What does the "Backlog" filter do?

This filter displays the tasks before being prioritized (example: Not started, Done, In progress, Next Up).

How do I apply the "Backlog" filter?

In order to apply the "Backlog" filter, go to menu Project - Filter and select Backlog or select More Filters and select Backlog and click on Apply button.

What does the "Created After..." filter do?

The "Created After..." filter allows seeing all tasks created after a specified date.

How do I apply the "Created After..." filter?

In order to apply the "Created After..." filter, go to menu Project - Filter and select More Filters and selectCreated After... and click on Apply button.

What does the "Critical" filter do?

The "Critical" filter allows seeing all tasks that are on a critical path.

How do I apply the "Critical" filter?

In order to apply the "Critical" filter, go to menu Project - Filter and select Critical or select More Filters and select Critical and click on Apply button.

What does the "Current Sprint" filter do?

The "Current Sprint" filter allows seeing all tasks from the current sprint.

How do I apply the "Current Sprint" filter?

In order to apply the "Current Sprint" filter, go to menu Project - Filter and select Current Sprintor select More Filters and select Current Sprintand click on Apply button.

What does the "Date Range..." filter do?

The "Date Range..." filter allows seeing all tasks that start or finish after the earlier specified date and before the later specified date.

How do I apply the "Date Range..." filter?

In order to apply the "Date Range..." filter, go to menu Project - Filter and select Date Range... or select More Filters and select Date Range... and click on Apply button.

What does the "Group" filter do?

The "Group" filter allows seeing all resources belonging to a specified group.

How do I apply the "Group" filter?

In order to apply the "Group" filter, go to menu Project - Filter and selectGroupor select More Filters and select Groupand click on Apply button.

What does the "Linked Fields" filter do?

The "Linked Fields" filter allows seeing the tasks to which information from other programs has been linked.

How do I apply the "Linked Fields" filter?

In order to apply the "Linked Fields" filter, go to menu Project - Filter andselect More Filtersthen select Linked Fieldsand click on Apply button.

What does the "Manually Scheduled Tasks" filter do?

The "Manually Scheduled Tasks" filter allows seeing all the manually scheduled tasks.

How do I apply the "Manually Scheduled Tasks" filter?

In order to apply the "Manually Scheduled Tasks" filter, go to menu Project - Filter andselect More Filters then select Manually Scheduled Tasks and click on Apply button.

What does the "Milestones" filter do?

The "Milestones" filter allows seeing only the tasks that are milestones.

How do I apply the "Milestones" filter?

In order to apply the "Milestones" filter, go to menu Project - Filter and select Milestones or select More Filtersthen select Milestonesand click on Apply button.

What does the "Resource Group..." filter do?

The "Resource Group..." filter allows seeing the tasks allocated to the resources belonging to a specified group.

How do I apply the "Resource Group..." filter?

In order to apply the "Resource Group..." filter, go to menu Project - Filterandselect More Filters then select Resource Group... and click on Apply button.

What does the "Resource Range..." filter do?

The "Resource Range..." filter allows seeing ll resources that have ID numbers within the specified range.

How do I apply the "Resource Range..." filter?

In order to apply the "Resource Range..." filter, go to menu Project - Filterandselect Resource Range... or selectMore Filters then select Resource Range... and click on Apply button.

What does the "Summary Tasks" filter do?

The "Summary Tasks" filter allows seeing all tasks that have subtasks.

How do I apply the "Summary Tasks" filter?

In order to apply the "Summary Tasks" filter, go to menu Project - Filter and select Summary Tasks or select More Filters and select Summary Tasks and click on Apply button.

What does the "Task Board Tasks" filter do?

The "Task Board Tasks" filter allows seeing all tasks created using Scrum methodology.

How do I apply the "Task Board Tasks" filter?

In order to apply the "Task Board Tasks" filter, go to menu Project - Filter and select Task Board Tasks or select More Filters and select Task Board Tasksand click on Apply button.

What does the "Task Range..." filter do?

The "Task Range..." filter allows seeing all tasks that have ID numbers within the specified range.

How do I apply the "Task Range..." filter?

In order to apply the "Task Range..." filter, go to menu Project - Filter and select Task Range... or select More Filters and select Task Range...and click on Apply button.

What does the "Tasks with a Task Calendar Assigned" filter do?

The "Tasks with a Task Calendar Assigned" filter allows seeing all tasks where a task calendar was applied.

How do I apply the "Tasks with a Task Calendar Assigned" filter?

In order to apply the "Task with a Task Calendar Assigned" filter, go to menu Project - Filter andselect More Filters thenselect Task with a Task Calendar Assignedand click on Apply button.

What does the "Tasks with Attachments" filter do?

The "Tasks with Attachments" filter allows seeing all tasks where a note or object was attached.

How do I apply the "Tasks with Attachments" filter?

In order to apply the "Task with Attachments" filter, go to menu Project - Filterandselect More Filters then select Task with Attachmentsand click on Apply button.

What does the "Tasks with Deadlines" filter do?

The "Tasks with Deadlines" filter allows seeing all tasks where a deadline was specified.

How do I apply the "Tasks with Deadlines" filter?

In order to apply the "Task with Deadlines" filter, go to menu Project - Filter andselect More Filters then select Task with Deadlinesand click on Apply button.

What does the "Tasks with Duration <8" filter do?

The "Tasks with Duration <8" filter allows seeing all tasks where task duration is less than 8 hours.

How do I apply the "Tasks with Duration <8" filter?

In order to apply the "Task with Duration <8" filter, go to menu Project - Filter and select More Filters then select Tasks with Duration <8and click on Apply button.

What does the "Tasks with Estimated Durations" filter do?

The "Tasks with Estimated Durations" filter allows seeing all tasks where duration is estimated.

How do I apply the "Tasks with Estimated Durations" filter?

In order to apply the "Task with Estimated Durations" filter, go to menu Project - Filter and select Tasks with Estimated Durationsor select More Flters and select Tasks with Estimated Durationsand click on Apply button.

What does the "Tasks with Fixed Dates" filter do?

The "Tasks with Fixed Dates" filter allows seeing all tasks that have an actual start date.

How do I apply the "Tasks with Fixed Dates" filter?

In order to apply the "Tasks with Fixed Dates" filter, go to menu Project - Filter and selectMore Filtersthen select Tasks with Fixed Datesand click on Apply button.

What does the "Tasks without Dates" filter do?

The "Tasks without Dates" filter allows seeing the manual tasks without start/finish date value inserted.

How do I apply the "Tasks without Dates" filter?

In order to apply the "Tasks without Dates" filter, go to menu Project - Filter and select More Filters then select Tasks without Datesand click on Apply button.

What does the "Top Level Tasks" filter do?

The "Top Level Tasks" filter allows seeing the highest-level summary tasks.

How do I apply the "Top Level Tasks" filter?

In order to apply the "Top Level Tasks" filter, go to menu Project - Filter and select More Filters then select Top Level Tasksand click on Apply button.

I would like to print only a set of selected rows of a big plan. For example, activities from 5 to 25. Is it possible in Project Plan 365 for Windows?

​You can print a set of selected rows by following the steps:
1. Go to menu tab Project and select Filter button
2. Then select filter by Task Range
3. It will appear a dialog. In the first text box put 5 and in the second one 25. Press Ok.

OR

1. Go to menu tab Project and select AutoFilter button
5. In task name column, create a filter to show only tasks from 5 to 25.
6. Then in Print Preview dialog you will see only tasks from 5 to 25 and you can print them.

How can I see only particular information from my project?

When you want to see a particular type of information you need to use filters. The application provides Predefined filters as well as Custom filters and Auto filters.

How can I highlight tasks that have a certain property?

To highlight tasks with a certain property click on Project - Filter - More Filters. Select a filter in the filter list and then click Highlight.

How do I add my favorite filters in the main Filter menu?

We are really sorry but at this point, it is not possible to add other Filters in the main Filter menu.

How to apply a custom field filter?

We are sorry, but at this point you cannot add a custom field filter. You can apply an autofilter.

What is Filter?

The filter option allows the user to view a particular type of information in the project by displaying only the information the user is interested in and hiding the rest.

Filters in Project Plan 365 (2024)
Top Articles
Investir em Fundos Imobiliários é seguro? Saiba se vale a pena
More Than 80 Percent of the World’s Oceans Remain Unexplored. These Scientists are Changing That.
Sprinter Tyrone's Unblocked Games
What Are Romance Scams and How to Avoid Them
Windcrest Little League Baseball
Hocus Pocus Showtimes Near Harkins Theatres Yuma Palms 14
1970 Chevelle Ss For Sale Craigslist
Devotion Showtimes Near Mjr Universal Grand Cinema 16
Stl Craiglist
Computer Repair Tryon North Carolina
Pollen Count Central Islip
Select Truck Greensboro
Zendaya Boob Job
Mens Standard 7 Inch Printed Chappy Swim Trunks, Sardines Peachy
Betonnen afdekplaten (schoorsteenplaten) ter voorkoming van lekkage schoorsteen. - HeBlad
Sams Early Hours
Rhinotimes
Committees Of Correspondence | Encyclopedia.com
Pizza Hut In Dinuba
Craigslist Appomattox Va
Air Traffic Control Coolmathgames
Used Safari Condo Alto R1723 For Sale
Ice Dodo Unblocked 76
Understanding Gestalt Principles: Definition and Examples
Dark Entreaty Ffxiv
Sandals Travel Agent Login
Hannah Palmer Listal
15 Primewire Alternatives for Viewing Free Streams (2024)
Random Bibleizer
Miles City Montana Craigslist
Askhistorians Book List
Log in or sign up to view
Leland Nc Craigslist
Newsday Brains Only
Baywatch 2017 123Movies
Soulstone Survivors Igg
When His Eyes Opened Chapter 2048
Temu Y2K
The Closest Walmart From My Location
Insideaveritt/Myportal
Fool's Paradise Showtimes Near Roxy Stadium 14
3 bis 4 Saison-Schlafsack - hier online kaufen bei Outwell
Nami Op.gg
Walgreens On Secor And Alexis
Haunted Mansion Showtimes Near Millstone 14
Bradshaw And Range Obituaries
Morgan State University Receives $20.9 Million NIH/NIMHD Grant to Expand Groundbreaking Research on Urban Health Disparities
Gameplay Clarkston
Leslie's Pool Supply Redding California
Latest Posts
Article information

Author: Neely Ledner

Last Updated:

Views: 6158

Rating: 4.1 / 5 (42 voted)

Reviews: 89% of readers found this page helpful

Author information

Name: Neely Ledner

Birthday: 1998-06-09

Address: 443 Barrows Terrace, New Jodyberg, CO 57462-5329

Phone: +2433516856029

Job: Central Legal Facilitator

Hobby: Backpacking, Jogging, Magic, Driving, Macrame, Embroidery, Foraging

Introduction: My name is Neely Ledner, I am a bright, determined, beautiful, adventurous, adventurous, spotless, calm person who loves writing and wants to share my knowledge and understanding with you.