Sentinel ICBM Exceeds Projected Cost by 37 Percent (2024)


March 2024
By Libby Flatoff

The U.S. Air Force notified Congress on Jan. 18 that the new Sentinel intercontinental ballistic missile (ICBM) would cost 37 percent more than expected and take about two years longer than planned to build and deploy.

Sentinel ICBM Exceeds Projected Cost by 37 Percent (1)The cost per unit for the Sentinel system originally was projected to be $118 million and now is estimated at $162 million, putting the projected total program cost at roughly $120 billion over the next decade, up from an estimated baseline of $96 billion, the Air Force told Defense News.

The expected delay of the system’s initial operating capability likely will result in greater sustainment costs to keep the existing fleet of Minuteman III ICBMs operational.

The projected overrun would put the new missile system in “critical” breach of the Nunn-McCurdy Act, a law designed to prevent major cost overruns for weapons systems, a chronic problem plaguing the Pentagon.

There are two levels of breaches under the act. A program is in significant breach when the program unit cost increases by 15 percent of the current baseline or 30 percent over the original cost estimate. A critical breach occurs when the cost increases by 25 percent of the current baseline or 50 percent of the original estimate.

In 2020, Northrop Grumman was awarded a sole-source $13.3 billion contract for engineering and manufacturing Sentinel missiles to replace the current arsenal of 400 deployed Minuteman III ICBMs.

The Sentinel development program calls for acquiring 659 missiles, updating 450 launch silos, and modernizing more than 600 facilities to “like new conditions,” according to Air Force Global Strike Command. (See ACT, May 2023.)

In 2020 the Pentagon estimated that the total cost of the next-generation Sentinel program, including decades of operations and support, could be as high as $264 billion. (See ACT, March 2021.) Taking the new cost increases into account, the total cost of the program over its planned 50-year life cycle could be as high as $300 billion, plus another $15 billion for the production of the new W87-1 warhead for the missiles.

Under the act, the Defense Department is required to report to Congress whenever a major defense acquisition program exceeds certain cost thresholds. The notification must include an explanation of the cost increase, changes in the projected cost, changes in performance or schedule, action taken or proposed to control cost growth, and prior cost estimating information.

In addition, the department must submit a new selected acquisition report containing the new status of the total program cost, schedule, performance, cost per unit, and cost breach information. The report on the Sentinel program is due to be submitted within 45 days after President Joe Biden submits his budget to Congress, now set for March 9.

With a critical breach, the Office of the Secretary of Defense is required to conduct a root-cause analysis to determine what factors caused the cost increase.

Under the act, if the program is to continue, the defense secretary must certify no later than 60 days after the new selected acquisition report that the program is essential to national security, the new cost estimates are reasonable, the program is a higher priority than those whose funding will be cut to cover the cost increase, and a new management structure is in place to control additional cost growth. If the certification and requirements are met, the program will be allowed to continue.

At the Air Force Association forum on Feb. 11, Air Force Secretary Frank Kendall said that “nothing is off the table right now.… [W]e’re going to take a look at the totality of the [defense] budget” when addressing how to cover the additional $35 billion needed for the Sentinel program.

Rep. John Garamendi (D-Calif.), a member of the House Armed Services Committee and co-chair of the bicameral Nuclear Weapons and Arms Control Working Group, argued in a statement Jan. 18 that the overrun is “proof that we must look closely at our nation’s nuclear policies…[and] address our security needs without compromising fiscal responsibility.”

Some experts, such as Gabe Murphy, a national security policy analyst with Taxpayers for Common Sense, say that the United States should get rid of ICBMs entirely. “Whatever strategic value nuclear ICBMs may have held in the past, in our current security environment, they serve as little more than a bottomless pit…[into] which the Pentagon throws taxpayers’ hard-earned money,” Murphy wrote in an Feb. 11 essay for Stars and Stripes.

In 2016, former Defense Secretary William Perry wrote in The New York Times “that the United States can safely phase out” its land-based ICBM force. He argued that although the ICBM force is too costly and dangerous, submarine and bomber forces are highly accurate and thus are “sufficient to deter our enemies and will be for the foreseeable future.”

Despite the cost increases, congressional backers of the Sentinel program say it should go full-speed ahead. “Sentinel is absolutely necessary for the future of our nuclear deterrent. I’m committed to conducting vigorous oversight of the program and ensuring the Air Force follows through on making the necessary changes to address the cost overruns while continuing to advance the program,” House Armed Services Committee Chairman Mike Rogers (R-Ala.) said in a Jan. 19 press statement.

Others urged support for Sentinel whatever the cost. “Despite these challenges, abandoning or downsizing Sentinel isn’t an option. Our nation’s safety and prosperity depend on an updated and fully operational nuclear deterrent,” argued Sens. Roger Wicker (R-Miss.) and Deb Fischer (R-Neb.), the ranking members of the Senate Armed Services Committee and its strategic forces subcommittee, respectively, on Jan. 19 in The Wall Street Journal.

Sentinel ICBM Exceeds Projected Cost by 37 Percent (2024)
Top Articles
Leading through Disruption: Netflix as the Disruptive Leader
DAP Shipping (Delivered at Place)
St Thomas Usvi Craigslist
Encore Atlanta Cheer Competition
Knoxville Tennessee White Pages
Is Sam's Club Plus worth it? What to know about the premium warehouse membership before you sign up
Danatar Gym
Tj Nails Victoria Tx
Exam With A Social Studies Section Crossword
Bucks County Job Requisitions
Lost Ark Thar Rapport Unlock
Mcoc Immunity Chart July 2022
Walgreens Alma School And Dynamite
Toonily The Carry
Rapv Springfield Ma
Athens Bucket List: 20 Best Things to Do in Athens, Greece
What Happened To Maxwell Laughlin
Busted Newspaper S Randolph County Dirt The Press As Pawns
Conan Exiles Thrall Master Build: Best Attributes, Armor, Skills, More
Steamy Afternoon With Handsome Fernando
2024 INFINITI Q50 Specs, Trims, Dimensions & Prices
Chaos Space Marines Codex 9Th Edition Pdf
Rubber Ducks Akron Score
Meta Carevr
Dashboard Unt
Craigslist Rentals Coquille Oregon
'Insidious: The Red Door': Release Date, Cast, Trailer, and What to Expect
Yale College Confidential 2027
Buhl Park Summer Concert Series 2023 Schedule
Combies Overlijden no. 02, Stempels: 2 teksten + 1 tag/label & Stansen: 3 tags/labels.
Package Store Open Near Me Open Now
DIY Building Plans for a Picnic Table
Street Fighter 6 Nexus
Rock Salt Font Free by Sideshow » Font Squirrel
Google Jobs Denver
What Are Digital Kitchens & How Can They Work for Foodservice
Metra Schedule Ravinia To Chicago
Hannibal Mo Craigslist Pets
USB C 3HDMI Dock UCN3278 (12 in 1)
Cal Poly 2027 College Confidential
Other Places to Get Your Steps - Walk Cabarrus
Wal-Mart 140 Supercenter Products
Beaufort SC Mugshots
Conan Exiles Armor Flexibility Kit
Www Craigslist Com Atlanta Ga
Chase Bank Zip Code
Bustednewspaper.com Rockbridge County Va
Fatal Accident In Nashville Tn Today
Greg Steube Height
The Sports Academy - 101 Glenwest Drive, Glen Carbon, Illinois 62034 - Guide
Terrell Buckley Net Worth
Tyrone Unblocked Games Bitlife
Latest Posts
Article information

Author: Errol Quitzon

Last Updated:

Views: 6319

Rating: 4.9 / 5 (59 voted)

Reviews: 90% of readers found this page helpful

Author information

Name: Errol Quitzon

Birthday: 1993-04-02

Address: 70604 Haley Lane, Port Weldonside, TN 99233-0942

Phone: +9665282866296

Job: Product Retail Agent

Hobby: Computer programming, Horseback riding, Hooping, Dance, Ice skating, Backpacking, Rafting

Introduction: My name is Errol Quitzon, I am a fair, cute, fancy, clean, attractive, sparkling, kind person who loves writing and wants to share my knowledge and understanding with you.