Work Breakdown Structure (WBS) As Defined in The Guide (2024)

Category: Project Management Professional (PMP)® Exam using A Guide to the Project Management Body of Knowledge (PMBOK® Guide)

Work Breakdown Structure (WBS) As Defined in The Guide (1)A work breakdown structure (WBS) in project management and systems engineering, is a tool used to define and group a project's discrete work packages in a way that helps organize and define the total work scope of the project. A work breakdown structure element may be a product, data, a service, or any combination. A WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control. Additionally the WBS is a dynamic tool and can be revised and updated as needed by the project manager.

One of the most important Work Breakdown Structure design principles is called the 100% Rule. This Rule states that the WBS includes 100% of the work defined by the project scope and captures all deliverables – internal, external, interim – in terms of the work to be completed, including project management. The 100% rule is one of the most important principles guiding the development, decomposition and evaluation of the WBS. The rule applies at all levels within the hierarchy: the sum of the work at the “child” level must equal 100% of the work represented by the “parent” and the WBS should not include any work that falls outside the actual scope of the project, that is, it cannot include more than 100% of the work. At the same time, it cannot contain only 95%. It must contain 100% of the work. It applies to the activity level. The work represented by the activities in each work package must add up to 100% of the work necessary to complete the work package.

A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Fifth Edition, states that Create WBS is the process of subdividing project deliverables and project work into smaller, more manageable components. The work breakdown structure (WBS) is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables, with each descending level of the WBS representing an increasingly detailed definition of the project work. The WBS organizes and defines the total scope of the project, and represents the work specified in the current approved project scope statement. The planned work is contained within the lowest level WBS components, which are called work packages. A work package can be scheduled, cost estimated, monitored, and controlled. In the context of the WBS, work refers to work products or deliverables that are the result of effort and not to the effort itself.

Read more about the WBS in the PMBOK®Guide.

Work Breakdown Structure (WBS) As Defined in The Guide (2024)
Top Articles
How To Quick Compost in 5 Easy Steps
Surgeon Sues Coinbase After $340,000 Hack
Victor Spizzirri Linkedin
Artem The Gambler
Craigslist Home Health Care Jobs
Ups Stores Near
Froedtert Billing Phone Number
craigslist: south coast jobs, apartments, for sale, services, community, and events
Needle Nose Peterbilt For Sale Craigslist
Grand Park Baseball Tournaments
Does Pappadeaux Pay Weekly
4156303136
Valentina Gonzalez Leaked Videos And Images - EroThots
Void Touched Curio
Erskine Plus Portal
7543460065
Sam's Club La Habra Gas Prices
Abby's Caribbean Cafe
Accident On 215
Program Logistics and Property Manager - Baghdad, Iraq
zom 100 mangadex - WebNovel
Georgia Cash 3 Midday-Lottery Results & Winning Numbers
Never Give Up Quotes to Keep You Going
Garnish For Shrimp Taco Nyt
Play It Again Sports Norman Photos
Saxies Lake Worth
Lacey Costco Gas Price
Expression Home XP-452 | Grand public | Imprimantes jet d'encre | Imprimantes | Produits | Epson France
Pokemon Inflamed Red Cheats
Town South Swim Club
Uno Fall 2023 Calendar
Ringcentral Background
R3Vlimited Forum
What Time Is First Light Tomorrow Morning
Best Restaurants In Blacksburg
Soulstone Survivors Igg
Ise-Vm-K9 Eol
Arcane Bloodline Pathfinder
Tgirls Philly
2013 Honda Odyssey Serpentine Belt Diagram
Matt Brickman Wikipedia
Graduation Requirements
Hdmovie2 Sbs
Mytmoclaim Tracking
Bradshaw And Range Obituaries
Used Auto Parts in Houston 77013 | LKQ Pick Your Part
Craigslist Indpls Free
Festival Gas Rewards Log In
Tenichtop
Predator revo radial owners
Affidea ExpressCare - Affidea Ireland
Latest Posts
Article information

Author: Stevie Stamm

Last Updated:

Views: 6691

Rating: 5 / 5 (80 voted)

Reviews: 95% of readers found this page helpful

Author information

Name: Stevie Stamm

Birthday: 1996-06-22

Address: Apt. 419 4200 Sipes Estate, East Delmerview, WY 05617

Phone: +342332224300

Job: Future Advertising Analyst

Hobby: Leather crafting, Puzzles, Leather crafting, scrapbook, Urban exploration, Cabaret, Skateboarding

Introduction: My name is Stevie Stamm, I am a colorful, sparkling, splendid, vast, open, hilarious, tender person who loves writing and wants to share my knowledge and understanding with you.